Building
Mail center around Paris

Storytelling
In connection with a 42M€ mall project on two levels, an estate company asked Argos Construction to analyze the reasons of the delays a consortium of companies had faced and explaining a 8 months delays for 18 months initially planned . The question was to establish the responsibility of each part as some internal disruptions had allegedly been regularized thanks to instructions to proceed though no agreement could be reached when this consortium asked for additional remuneration. Argos Construction then performed a careful delay analysis to understand the link between each issue and their cumulative impact, and to determine how some external disruptions had taken place in the global scheme at the same time.

Mail center around Paris
  • Mission

    Analysis of the critical events for a private Employer within a judicial expertise which opposes him to the General Contractor  because of the project delays of 8 months.

  • Objectives

    Analysis of all contractual, administrative and technical documents ;

    Analysis of the unit and cumulative impacts on delays of each modification brought to the project ;

    Analysis of the unit and cumulative impacts on delays of the General Contractor events.

  • Challenges

    Delays of 8 months for initial duration of 18 months ;

    15,5 M€ for a contract of 42 M€ (37%)

  • Outcome

    Report provided and the proceeding is actually on going.