Civil works
potable water conveyance Maghreb

Potable water conveyance Maghreb
  • Mission

    Review of the claims presented regarding the delay of 19.3 months in the construction and commissionning of a hydraulic pipe connecting the pumping station to the dam (5 major civil works including a tunnel).

  • Objectives

    Review of contractual data ;

    Analysis of durations of major works for a global synthesis ;

    Quantification of extra costs and damages ;

    Establishment and presentation of the report ;

    Review of correspondences / amendments within a contract management mission ;

    Participation to arbitration hearings (ICC).

    • Challenges

      Delays of 19.3 months for initial duration of 27 months ;

      128 M€ for a contract of 108 M€.