Railway France

Storytelling
This case has to be considered in parallel with the precedent one. The Employer introduced many modifications in a railway project which resulted in amendments because of some technical uncertainties. However those amendments did not present proper figures. Thanks to critical path analysis and a careful analysis of the critical events, first, the amendments were rectified; secondly, following events and changes could be anticipated. A new time schedule was established as well as a new assessment of costs. Argos was able to improve the situation in emphasizing the difficulties met.  Then both parties decided to extend the contract. 

Railway France
  • Mission

    Assistance in the preparation of the statement of claim for an additional remuneration resulting from the technical changes and according to the contract performance clauses.  

  • Objectives

    Analysis of  the contractual documents and of the administrative and technical records 

    Review of the documents

    Critical Path Analysis: reconstruction of the disruptive events, causes and consequences

    Delay analysis and financial impacts

    Review of the calculation

    Preparation of the statement (argument and written document)

    Assistance in the discussions and review of the amendment or correspondence projects until the decision concerning the completion of work is notified.

    • Challenges

      1 month and 2 weeks delay for a period of 4 months and 2 weeks

      2M€ for a 9,5M€ contract