Contractual Management
Creation of a database allowing to follow the studies as well as to track disruptions.
Implementation of a follow-up to works « as built ».
Review of project of letter expressing reservations about the instructions to proceed, correspondence.
Management of the prescriptive dates.
Good practices in contractual management, including drafting documents, anticipation and and need to alert, handling with FTM / FMP and additional works training of the work team.
23 months extension of time for 25 months initially planned
0,8 M€ additional remuneration for 3 M€ contract
The extension of time has been regularised (removal of liquidated damage) and a 0,4 M€ transaction obtained