Tramway France

Storytelling
Thanks to a contract management implementation since the beginning of the project, all the events have been recorded. The contractor had regular reports with all requested details. Amendments were thus immediately agreed upon as well as additional payments. This case constitutes the exact opposite of the previous one. The Employer was regularly informed with events and dispute has been avoided.

Tramway France
  • Mission

    Preparatory review 

    Contractual gestion

    Statement of claim

  • Objectives

    Contractual terms analysis 

    Analysis of the challenges related to the delays in the execution

    Determination of the calculations

    Preparation of a project of a request for additional remuneration 

    Review of the events able to justify a claim.

    Review ogf the exchanges and steps concerning the contract management.

    Preparation of a second statement of claim for additional remuneration in respect of the challenges which have been determined and of the defined strategy.

    • Challenges

      24 months delay for  20 months initially planned

      4 M€  additional remuneration +150 K€ remission of liquidated damage for a 38 M€ HT contract

  • Outcome

    /