Preparatory review
Contractual gestion
Statement of claim
Contractual terms analysis
Analysis of the challenges related to the delays in the execution
Determination of the calculations
Preparation of a project of a request for additional remuneration
Review of the events able to justify a claim.
Review ogf the exchanges and steps concerning the contract management.
Preparation of a second statement of claim for additional remuneration in respect of the challenges which have been determined and of the defined strategy.
24 months delay for 20 months initially planned
4 M€ additional remuneration +150 K€ remission of liquidated damage for a 38 M€ HT contract
/