Establishment of claim for additional remuneration to include in the final statement.
Present the major contractual data;
Justify the execution of additional works essential to the project;
Recount the story of underwent disruptions;
Justify the extension of time of the contractor taking into account the underwent disruptions;
Analyze the consequences on means mobilization resulting of disruptions and of the extension of time;
Establish of quantification of additional costs and damages.
Extension of time by 1 month of the 5 months initially planned;
100 k€ additional remuneration for a 200 k€ contract amount.
Administrative Court decision: 85 k€