Landscaping Works South of France

Storytelling
Important delays appeared during landscaping works and the claim presented during the final statement has been rejected by the Employer. The contractor who is a small company has assigned to the Administrative Court the Employer. In the context of the legal expertise, the intervention of Argos Construction with the Contractor as a technical advisor for the establishment and the review of its statements, has contributed to obtain 85k€ as the Court’s decision for a claim of 100 k€.

Landscaping Works South of France
  • Mission

    Establishment of claim for additional remuneration to include in the final statement.

  • Objectives

    Present the major contractual data;

    Justify the execution of additional works essential to the project;

    Recount the story of underwent disruptions;

    Justify the extension of time of the contractor taking into account the underwent disruptions;

    Analyze the consequences on means mobilization resulting of disruptions and of the extension of time;

    Establish of quantification of additional costs and damages.

    • Challenge

      Extension of time by 1 month of the 5 months initially planned;

      100 k€ additional remuneration for a 200 k€ contract amount.

  • Outcome

    Administrative Court decision: 85 k€