Office Building South of France

Storytelling
This case took place in a sensitive context of painting works which are exposed to damages and the lesser modification has important impacts on manpower cost. Furthermore delays in works handing over have generated an increase of 37% of the durations. However the unexperienced team in contract management was unable to prove his statements. Argos Construction presented the claim and has shown to the Employer that he had not only a truncated vision of the actual situation but also the contractor was working with rigor and that lead it to get new contracts.

Office Building South of France
  • Mission

    Establishment of claim for additional remuneration 

  • Objectives

    Justify the shift of the contractor’s works in accordance with the encountered disruptions ;

    Quantification of extra costs and damages.

    • Challenge

      Extension of time of 3 months for a 8 months initially planned ;

      100 k€ compensation for a contact amount of 300 k€

  • Outcome

    First the contractor’s claim has been rejected

    Assistance in the case follow up and in debarment periods management ;

    Negociation of a settlement of 60 k€